Construction Progress Report
Riverside Phase 2 - visit 7
| Report reference | AER-2026-198 |
|---|---|
| Client | Kestrel Construction, c/o M. Ivanova, project manager |
| Site | Riverside Phase 2, Plovdiv |
| Visit number | 7 of 14 |
| Date of survey | 18 June 2026 |
| Previous survey | 21 May 2026 - report AER-2026-171 |
| Surveyed by | A. Petrov, operator BGR-OP-4471 |
1. Summary
Aerial survey 7 of Riverside Phase 2 was flown on 18 June 2026, 28 days after the previous visit.
| This visit | Previous visit | Change | |
|---|---|---|---|
| Area with slab poured | 3,420 m2 | 2,180 m2 | +1,240 m2 |
| Frame erected - floors | 4 | 2 | +2 |
| Stockpile volume, north compound | 1,860 m3 | 2,410 m3 | -550 m3 |
Against programme: broadly on schedule for the frame, approximately 10 days behind on the podium slab, based on the programme issued on 4 April 2026.
2. Scope
Periodic aerial photographic record of the whole site for progress monitoring and record purposes.
Not within scope: quality inspection, workmanship assessment, compliance checking, structural assessment, setting-out verification, statutory health and safety inspection.
A worked section, from later in the report
| Ref | Location | Observation | Raised with |
|---|---|---|---|
| O-01 | Zone A, level 2 east | Edge protection absent to approx. 6 m of slab edge | Site manager, 18/06/2026 |
| O-02 | Haul road, south | Standing water across full width, approx. 12 m | - |
| O-03 | Zone C compound | Materials stacked within the crane oversail area | - |